Completion of Road 1095 repairs delayed as much as two weeks

A county official says three of the four culverts to be used on phase one of the project on County Road 1095 were damaged and need to be replaced. It will delay reopening of the road as much as two weeks. (Photo by Roger Sims / Linn County Journal)
A county official says three of the four culverts to be used on phase one of the project on County Road 1095 were damaged and need to be replaced. It will delay reopening of the road as much as two weeks. (Photo by Roger Sims / Linn County Journal)

By Roger Sims


LA CYGNE – A contractor working to replace culverts on County Road 1095 near the intersection of 2075th Road inadvertently crushed three of the four culverts in the first phase of the project.


While the damaged culverts were replaced by last Friday, Aug. 21, new culverts will need to be ordered for the second phase of the project.


Since the large culverts are custom made, it could take at least two weeks before they are delivered, J.D. Handly, public works director for Linn County, told the Linn County Commission on Monday, Aug. 24.


The paved road, which connects La Cygne with the Tanglewood Lakes development as well as points south to Mound City, has been out of commission since early August and now appears to be closed until nearly mid-September.


In addition to being an inconvenience for area residents, the delayed opening of the road is also expected to conflict with schedule with repaving the repair.

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
An official news publication for the city of La Cygne, Kansas,
and Prairie View Unified School District 362
Screenshot 2026-02-09 at 12.53.08 PM.png

Content may be copied for personal use only. All content copyright©2026 Linn County Journal and may be used for re-publication only with written consent by the publisher. © 2026 by TheHours. Proudly created with Wix.com

bottom of page